TheLawyer.sh
Tilbage

Commission Decision (EU) 2024/1274of 29 April 2024granting the Hellenic Republic a derogation from certain provisions of Regulation (EU) 2019/943 of the European Parliament and of the Council and of Directive (EU) 2019/944 of the European Parliament and of the Council, as regards the island of Crete(notified under document C(2024) 2890)(Only the Greek text is authentic)(Text with EEA relevance)

32024D1274

Den Europæiske UnionAfgørelse2024

European Union

§ Article 6

Article 6, Article 7(1), Article 8(1) and (4), Articles 9, 10 and 11 of Regulation (EU) 2019/943

4.2.1.1.

The Application

(32) With regard to Article 6 of Regulation (EU) 2019/943, Greece submitted that the hybrid model currently applicable in the island of Crete does not include a balancing market. Hence a derogation from that Article would be necessary for the hybrid model to continue to apply until the island of Crete is fully interconnected.

(33) With regard to Article 7(1) and Article 8(1) and (4) of Regulation (EU) 2019/943, Greece notes that the hybrid model as currently applicable in the island of Crete does not provide for day-ahead and intraday markets, or trades on either of these markets. Hence, according to Greece, a derogation from those Articles would be necessary for the hybrid model to continue to apply until the island of Crete is fully interconnected.

(34) Likewise, following on from what is set out in recital 33, Greece considers that the integration of forward markets, technical bidding limits and the value of lost load referred to in Articles 9, 10 and 11 of Regulation (EU) 2019/943 do not apply to the hybrid model in the island of Crete. Hence, according to Greece, a derogation from those Articles would be necessary for the hybrid model to continue to apply until the island of Crete is fully interconnected.

4.2.1.2.

Assessment

(35) With respect to the requested derogation from Article 6, Article 7(1), Article 8(1) and (4) and Articles 9, 10 and 11 of Regulation (EU) 2019/943, those provisions refer to requirements regarding the forward, day-ahead, intraday and balancing markets. Based on the information submitted by Greece, it appears that those markets cannot be implemented effectively in the island of Crete considering the particularities of the electricity system currently applicable in that territory. Hence, a derogation from those provisions is justified.

4.2.2.

§ Article 40

Article 40(4) to (7) of Directive (EU) 2019/944

4.2.2.1.

The Application

(36) Greece submitted that the hybrid model does not provide for a balancing market or market-based procurement of ancillary services. In order for the hybrid model to continue operating in the transitional period, a derogation from that Article would be necessary.

4.2.2.2.

Assessment

(37) Given the absence of a balancing market and of a market-based procurement of non-frequency ancillary services in the island of Crete, a derogation from the obligations in Article 40(4) to (7) of Directive (EU) 2019/944 is justified.

4.3.

No obstruction to the transition towards renewable energy, increased flexibility, energy storage, electro-mobility and demand response

(38) Pursuant to Article 64(1), fifth subparagraph, of Regulation (EU) 2019/943 and Article 66(2) of Directive (EU) 2019/944, a derogation decision is to ensure that it does not obstruct the transition towards renewable energy, increased flexibility, energy storage, electro-mobility and demand response.

(39) As regards the transition towards renewable energy and increased flexibility, including demand response, and energy storage, it should be noted that well-functioning forward, day-ahead, intraday and balancing markets, in accordance with the requirements set in Regulation (EU) 2019/943 and Directive (EU) 2019/944 should provide the necessary dispatch and investment signals to maximise the potential development of those technologies. This is expected to be the case once the island of Crete is fully interconnected with mainland Greece.

(40) As indicated in recital 56 of Decision (EU) 2022/258, prior to the completion of the Phase I interconnection, technical limitations were applied to Crete, imposing a maximum penetration of renewables to 25 % of the load, due to operational security constraints. The completion of Phase I relieved, to a certain extent, that limitation imposed on renewables. The hybrid model allows Crete to export its electricity in case of low load and high renewables generation, in order to avoid curtailment of renewables. Greece submitted figures in support of that statement, demonstrating that during 2021 and especially 2022, which marked the first full year of the operation of the Phase I interconnection, there was an increase in RES production compared to previous years.

(41) Greece notes that the requested derogation will not slow down the already ongoing development and preparation for the installation of new RES capacities on the island of Crete. Greece also submitted that upon completion of the full interconnection, Crete will accommodate at least 2150 MW of RES, which, considering the installation of storage units, may increase to 2500 MW.

(42) As regards increased flexibility, energy storage and demand response, the possibility of offering flexibility services, including storage, to support the electric system depends on the quality of the price signals and their ability to provide efficient investment and dispatch incentives to the providers of those services. As a rule, structural congestion within a bidding zone, which will be the case during the transitional period from Phase I to Phase II, can result in distorted investment signals for location-specific flexibility services. However, in a two-bidding zones approach for Crete and mainland Greece, the investment signals would be highly unstable, given the timeframe for the completion of Phase II and the full interconnection of Crete to mainland Greece, which will relieve structural congestion. Therefore, since the connection to the mainland will enable market-based provision of flexibility services, a short-term derogation which enables rapid integration of Crete into the mainland system is beneficial to the integration of demand response, energy storage and other flexibility sources.

(43) Article 64 of Regulation (EU) 2019/943 does not require that derogation decisions maximise the potential for flexibility or energy storage. A derogation under that Article only aims to ensure that it does not obstruct such transition. In other words, the derogation should not prevent developments which, without the derogation, would occur naturally. It is unlikely that, absent the derogation, well-functioning forward, day-ahead, intraday and balancing markets would develop in each of the electricity systems in the island of Crete. This is due to the challenges linked to the operation of the small connected electricity systems, the very low levels of competition in the generation segment, and the lack of connection to the mainland market. In that respect, the limited duration of the derogation, and the readiness for a full market operation as soon as Phase II is completed, is of utmost importance.

(44) Given its short-term nature, the hybrid model does not appear to have a noticeable impact on the further development of renewable energy, flexibility, energy storage, electromobility and demand response.

(45) Finally, Article 64(1) of Regulation (EU) 2019/943 requires the Commission to set out to what extent the derogation is to take into account the application of the network codes and guidelines. In this case, except for the provisions affected by the scope of the derogation detailed in recitals 32 to 37, the network codes and guidelines are, and are to remain, applicable to the island of Crete.

4.4.

Limitation of the derogation in time and conditions aiming to increase competition and integration with the internal market for electricity

(46) Article 64 of Regulation (EU) 2019/943 and Article 66 of Directive (EU) 2019/944 expressly set out that the derogation is to be limited in time and is to be subject to conditions aiming to increase competition and integration with the internal market for electricity.

(47) In light of the reasons put forward by Greece in recital 19, the new derogation request is limited to the transitional period ending on 31 December 2025 at the latest.

(48) It is understood that by 31 December 2025 the interconnector between Crete and the Greek continental system is expected to be operational, together with the appropriate metering infrastructure enabling Crete to become part of the Greek wholesale electricity markets. Greece confirmed that there will not be any further delay to the completion of the interconnection project.

4.5.

Time of effect

(49) While the Application was received on 18 December 2023, it was not possible to adopt this decision before 31 December 2023, at which point the derogation granted in Decision (EU) 2022/258 expired. In order to avoid rapid and unpredictable changes of the regulatory framework for the period between 1 January 2024 and the date of adoption of this Decision, which could seriously harm market functioning on the island of Crete and possibly in mainland Greece, this Decision should apply from the date following the end date of the derogation granted in Decision (EU) 2022/258, namely from 1 January 2024.

HAS ADOPTED THIS DECISION:

Article 1

A derogation is granted to the Hellenic Republic from the provisions of Article 6, Article 7(1), Article 8(1) and (4) and Articles 9, 10 and 11 of Regulation (EU) 2019/943 and from the provisions of Article 40(4) to (7) of Directive (EU) 2019/944, as regards the island of Crete.

Article 2

The derogation granted under Article 1 shall apply from 1 January 2024 until 31 December 2025 or until the completion of Phase II of the interconnection between Crete and mainland Greece, whichever comes first.

Article 3

The Hellenic Republic shall inform the Commission in two instances, first by 31 December 2024 and second by 30 June 2025, of the progress and remaining planning towards the completion and commercial operation of Phase II of the interconnection between Crete and mainland Greece, including regarding the deployment and operation of the adequate metering infrastructure allowing the participation of Crete in the Greek wholesale and balancing market.

Article 4

This Decision is addressed to the Hellenic Republic.

Done at Brussels, 29 April 2024.

For the Commission

Kadri Simson

Member of the Commission

Metadata

Type
Afgørelse
År
2024
Ikrafttrædelsesdato
1. januar 1970
Commission Decision (EU) 2024/1274of 29 April 2024granting the Hellenic Republic a derogation from certain provisions of Regulation (EU) 2019/943 of the European Parliament and of the Council and of Directive (EU) 2019/944 of the European Parliament and of the Council, as regards the island of Crete(notified under document C(2024) 2890)(Only the Greek text is authentic)(Text with EEA relevance) | TheLawyer.sh